Production question CAT330 and 345?

LDK ยท 2008-02-10 06:58

Could any one tell me how many cubic meters ( or yards) you can expect to move per hour when loading clay into trucks with a Cat 330? The same question again but for a Cat 345. An average figure will do, assuming that the machine is not waiting for trucks. Thank you in advance. Russell

Replies7
  1. #1pushcat2008-02-10 08:59

    Way too many variables and not enough info to figure properly. Just a rough guess but figure a 3yd scoop every 30 seconds = 460 yds/hr.

  2. #2CarterKraft2008-02-10 10:55

    anyone who asks a question likes this needs a CAT PErformance Handbook, it is full of information like this for all types of machines.

  3. #3Turbo218352008-02-10 13:10

    Cat handbook says a 330 D with a 1.83 cuyd bucket and a 345C with a 3.0 cuyd bucket should make three cycles per minute, in clay, with an average operator, and a 60 deg to 90 deg swing angle. It may be a little less while loading trucks depending the operator.Using these numbers The 330D should move 5.49 yds a minute, assuming your machine is able to work 50 minutes our of each hour that means 274.5 cuyd an hour. The 345C should move 9 yards a minute, same with the 330D aprox 50 min of work each hour, that means 450cuyd an hour. Again, there are a lot of variables, so this is a rough guess, and really depends on how many trucks you have, plus that assumes you can get the trucks under the bucket fast enough. From personal experience, Running a Komatsu pc300, with a 2 yard bucket, in a 12 hour day, with 15 trucks on a 4 mile round trip, i was able to load out 3,800 cuyds. in a day. Roughly 316 cubic yards an hour. No stopping for lunch of break. Minimal waiting for trucks. All in all, perfect conditions.

  4. #4LDK2008-02-10 13:40

    Pushcat, thank you, I was only looking for a rough idea.

  5. #5danhoe2008-02-10 15:07

    Is it stock piled Another factor is the dirt in a pile or still in the ground. (Hey Turbo) danhoe

  6. #6crazycajun2008-02-10 22:52

    well i have a 3yd bucket on 330cl and have loaded 4100 yards from a shelf, and a 4yd bucket on 345cl and have loaded 5500 yards. but cant really tell exactly how many voids the trucks had....

  7. #7danhoe2008-02-11 06:49

    Divide how many trucks by the yards you loaded, & how much the trucks hold, that will give you a pretty good idea. Danhoe