Just finished the 1st phase of my first base rock job, amount bid 4520 ton amount delivered 4513 ton whew , the trucks had a 2 hour loop so the material was high @ $366 a load so being off is deadly. Math is good, figured 5% extra to compensate for moisture weight.
7 ton.... now you have money left over for BEER good job... your better put that calculator in a safe place...
It always made me feel good when the boss told me how close I was to what he figured the job for.I enjoy finish work.Ron G
Well Done!
Says 2 things. Your math was good, and your finish was excelent.
Thanks guys but all I really did was calc the Sq Ft. The formula I had and Topcon did the rest, we used the topcon on the sub grade as well as finish rock. I like the work it uses much less fuel than bulking dirt and is easy on equipment and since I was on the water truck part of the time I never got my azz chewed for getting it to wet
Damn good job:notworthy