Moving 1.2 million yards! PICS

Kman9090 ยท 2010-08-16 22:32

We started on this job around april and now we are just starting august and have moved over half the dirt! We started off with only 10 john deere 9630s pullin 2 18 yard e-ject pans, basically they were building the haul roads and getting everything ready for the 631's! We are currenley running 7 john deere 9630s, 15 631's, and 3 623's! 385 diggin out the creek crossing to build a temporary crossing building the haul road from are borrow area to are fill, it was aroun a mile haul from the pit to the fill pushing a ramp down the hill so the john deers could climb it john deeres stuck roll over

Replies5
  1. #1Kman90902010-08-16 22:39

    blade dressing up the slope lime trucks stuck pushing another ramp off for the 31's my new dozer 15 631's

  2. #2Cat Wrench2010-08-17 01:10

    What company? Where is the job located?

  3. #3Kman90902010-08-17 20:50

    Shreveport LA! And its TJ Lambrecht

  4. #4JimBruce422010-08-17 21:09

    Nice pics. Looks like a fun job. Was the 385 there for pipe or was it bulking dirt too?

  5. #5Kman90902010-08-17 23:14

    385 was brought there for pipe but will be loading 20 belly dumps in a few weeks! We have a 3 mile haul to do and i dont think they want to do it with 31's!