How do you calculate the amount of sand needed for a sand mound?Thanks for any help

Replies6
  1. #1Maola2012-06-25 17:15

    sand mound ??? HxWxL devided by 27 i think

  2. #2SeaMac2012-06-25 18:01

    Yep, LxWxH divided by 27 = cubic yards

  3. #3CM19952012-06-25 20:34

    I am assuming this is a sand mound for a septic leach field? First of all determine the dimensions from the engineers plan and then use the formula's posted above. Don't forget a swell or shrink factor, as that will determine how much sand you need to truck in. For instance (HxWxL)/27= Cubic yards, then multiply that amount by the swell factor (for sand it can be 30-40%). The formula would be: HxWxL = Total cubic feet, divided by 27 = Cubic yards. Multiply the cubic yards by the swell factor in this case 1.3 or 1.4 = total CY's needed. This would be the amount you would have to truck in. Swell factors - http://www.engineeringtoolbox.com/soil-rock-bulking-factor-d_1557.html

  4. #4hougie2012-06-25 21:37

    Learned something new today, how to get cubic yards, thanx guys!!!

  5. #5CM19952012-06-25 21:42

    That's what we're all here for. Even easier when using the metric system, if your HxWxL is in meters, no need to divide by 27 to get cubic meters.

  6. #6grandpa2012-06-26 21:46

    and divide the yards by 1.4 (on average) to get the tons.